ARMY AL&T
“We pulled out all the stops to collapse the schedule and get these vehicles into theater,” said BG Michael Brogan, Commander, U.S. Marine Corps (USMC) Systems Command and Joint Program Executive Offi cer (PEO) MRAP Program. “We are doing everything required to ensure that they are safe, that the risk assessments are complete, and that they’re fully integrated and fl own into Afghanistan.”
Rapid Acquisition Procurement of the M-ATV grew from an urgent requirement to pro- vide troops a survivable, yet smaller and more maneuverable, vehicle that can travel off-road and navigate Afghanistan’s diffi cult, mountainous terrain. Drawing from lessons learned from the procurement of baseline MRAPs for Operation Iraqi Freedom (OIF ), the JPO devised and executed a rapid acquisition strategy.
The core effort began in June 2008 in response to a draft Army Operational Needs Statement for a lighter MRAP that could maneuver in the Operation
Enduring Freedom (OEF ) terrain. By August, a Request for Information was released to test the industrial base and see if the requirements were possible to develop. The government received 30 proposals. Two months later, the Joint Urgent Operational Needs Statement (JUONS) was signed and the source selection effort expanded to begin an intensive and rigorous requirements evaluation, with a Request for Proposal (RFP) released in December. The RFP provided an anticipated initial buy of 2,080 vehicles, with a maximum ceiling of 10,000.
Under this accelerated, best-value acquisition, offerors were required to meet three main screening criteria: vehicle weight was not to exceed 25,000 pounds; vehicles were to
accommodate a crew of fi ve; and vehicles had to pass ballistics tests. In January 2009, industry responded with eight offerors submitting proposals. Those selected in the fi rst round in February received contracts to build and deliver two test vehicles that went through ride, mobility, and ballistic testing at Aberdeen Test Center (ATC), MD. Those vehicles that met basic requirements were accepted for armor, ballistic, and mobility testing.
On April 30, 2009, the government awarded fi ve indefi nite-quantity indefi nite- delivery contracts for additional test vehicles. The competition included Oshkosh Defense, BAE Global Tactical Systems, BAE U.S. Combat Systems, Navistar Defense, and Force Dynamics (a joint venture between
Drawing from lessons learned from the procurement of baseline MRAPs for OIF, the JPO devised and executed a rapid acquisition strategy.
The acquisition effort for the M-ATV is unprecedented, even more so than the original MRAP effort. Production began in July 2009 and the fi rst trucks were fi elded to the USMC in Afghanistan on Dec. 6, 2009, just 160 days from contract award. (Photo courtesy of MRAP JPO.)
APRIL –JUNE 2010 23
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72