search.noResults

search.searching

dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
ARMY AL&T


Background: American Recovery and Reinvestment Act (ARRA) The authors’ presentation of the U.S. case focused on procurement’s role in the execution of the ARAA. Signed into law by President Barack Obama in February 2009, ARRA provides for a variety of stimulus measures with a potential value of almost $790 billion. It is intended to provide quick and effective stimulus for the economy by injecting financial resources into key sectors. Elements of ARRA include direct cash payments, tax credits and benefits for both individuals and firms, funds for state and local governments to maintain essential health and education programs, and investments in infrastructure.


Procurement plays a key role in ARRA, since grants and contracts are the principal means by which the ARRA funds will be obligated. ARRA gives preference to so-called “shovel-ready” projects; that is, activities that can be started and completed expeditiously. According to Office of Management and Budget (OMB) guidance, agen- cies must ensure that public funds are expended responsibly and in a trans- parent manner to further job creation,


economic recovery, and other purposes of the ARRA.


The Port of Oakland Project Since the USACE executes a significant number of construction and infrastruc- ture projects, it provided an excellent example of an ARRA project for pre- sentation at the Lisbon workshop. The specific project, accomplished by the USACE’s San Francisco, CA, District of the South Pacific Division, entailed the acceleration of existing interre- lated projects to improve the Port of Oakland—the second largest port on the West Coast and the fifth largest container port in the Nation—and restore environmentally sensitive wet- lands near Hamilton Airfield several miles north of Oakland.


The deepening project increased the channel depth of the Oakland Harbor and Port berths from 42 feet to 50 feet. At this new depth, the port can accommodate much larger vessels, including a new generation of very large “post-panamax” ships. It also allows for container ships to increase loads by 60 percent.


Approximately 3 million cubic yards of sediment dredged for this project


contributed to environmental enhance- ment and wetland habitat at Hamilton Airfield. The Hamilton Wetlands Restoration Project, currently USACE’s largest restoration project with nearly 2,500 acres of wetlands restoration, holds more than 24 million cubic yards of beneficial reuse dredge mate- rial. Endangered species that will derive protection from this portion of the proj- ect include the clapper rail and the salt marsh harvest mouse. Without this por- tion of the project, the dredged materials would have to be transported to a dis- posal location well out in the Pacific Ocean with substantially higher costs and increased risks (technical, environ- mental, safety, etc.) in several areas.


The project began in 2006 and was originally scheduled to be completed no earlier than December 2011, assuming the project was fully funded. By apply- ing ARRA funds to this “bucket-ready” project, it was modified to accelerate its completion date to January 2010. According to the contractor, a sub- stantial number of jobs were thus saved, and the project was successfully completed months ahead of schedule, thereby allowing for a more rapid real- ization of the economic benefits of the harbor improvements.


In terms of accomplishing ARRA objectives, three major elements of the USACE response are evident in this project:


• Procurement spending (injecting capital into the private sector).


• Improved transportation infrastructure.


• Secondary economic benefits (e.g., growth of San Francisco Bay area commerce).


Challenges and Successes in Execution


Key individuals work on the Oakland-Hamilton contract. From left to right: York So, Civil Engineer, Cost Engi- neering Section; Bick Lee, Civil Engineering Tech, Cost Engineering Section; James Garror, Contract Specialist, Contracting Division; Al Paniccia, Project Manager, Programs and Project Management Division; and Dave Doak, Project Manager, Programs and Project Management Division. (Photo by Brandon Beach, USACE San Francisco District.)


The project was initiated in 2006 when the USACE project manag- er organized a 2-day teambuilding session that included all major


JULY –SEPTEMBER 2010 83


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96