In addition to the new munition, the APMI system required the development and urgent material release (UMR) of fire control software for both the M32 Lightweight Handheld Mortar Ballistic Computer and the M150/M151 Mortar Fire Control System. It also required the development and UMR of a new setter system to program fuze setting, target location, and guidance information into the cartridge before it is fired. The XM701 Precision Lightweight Universal Mortar Setter System (see Figure 2) includes the M1155A1 Enhanced Portable Inductive Artillery Fuze Setter (EPIAFS), already developed and fielded for the Excalibur 155mm artillery projectile.
This work, to include follow-on produc- tion to support fielding, was all performed in-house by the Armament Research, Development, and Engineering Center at Picatinny Arsenal.
ACQUISITION OBJECTIVES The three essential aspects of this acqui- sition were speed, precision, and safety. These three aspects shaped everything from Integrated Product Team makeup to the contract vehicle and acquisition strat- egy. Given the initial theater requirements and nonnegotiable safety requirements, the PM office immediately engaged the combat developer at the U.S. Army Maneuver Cen- ter of Excellence, Fort Benning, GA, and the U.S. Army Test and Evaluation Com- mand, Aberdeen Proving Ground, MD, to scope the detailed performance, test, and evaluation requirements for the system.
Speed in delivery required a nontraditional approach to acquisition. The fastest path to fielding was to select a robust design that required little to no design effort and to award the production contract as early as possible. Using an existing DOD Ord- nance Technology Consortium contract was key to expediting the contract award.
(SOURCE: PEO Ammo.)
The inherent risk in an early production award was that the Army might buy hard- ware that could not be used for fielding. To mitigate this risk, PEO Ammo made three key decisions:
• Conduct a full and open competition with the technical, schedule, and early production goals of the program fully described and assessed upfront.
• Conduct extreme environmental quali- fication testing on all proposed designs involved in the competitive shoot-off before selection of the design that would go forward. Thus, performance issues would be identified and assessed in advance using gun-fired test data.
• Limit the initial production award to approximately 25 percent of the total quantity, with the remainder to be awarded after successful completion of qualification.
COMPRESSED TIMEFRAME In February 2010, extreme environmental conditioning and a competitive shoot-off were held at Yuma Proving Ground, AZ, to evaluate and compare cartridges devel- oped by several companies. This led to an April 2010 selection of the design submit- ted by Alliant Techsystems Inc. (ATK) for qualification and fielding to OEF.
In June 2010, a contract was awarded to ATK for limited production to meet the urgent need in theater.
Qualification of the cartridge was com- pleted in January, along with the First Article and Acceptance Test of the first production lot. UMR of the XM395 cartridge occurred on March 3, and the UMR of the setter and fire control soft- ware updates occurred the next day.
AS
C.ARMY.MI L 31
Supporting Systems for APMI Figure 2
ACQUISITION
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100 |
Page 101 |
Page 102 |
Page 103 |
Page 104 |
Page 105 |
Page 106 |
Page 107 |
Page 108 |
Page 109 |
Page 110 |
Page 111 |
Page 112 |
Page 113 |
Page 114 |
Page 115 |
Page 116 |
Page 117 |
Page 118 |
Page 119 |
Page 120 |
Page 121 |
Page 122 |
Page 123 |
Page 124 |
Page 125 |
Page 126 |
Page 127 |
Page 128 |
Page 129 |
Page 130 |
Page 131 |
Page 132 |
Page 133 |
Page 134 |
Page 135 |
Page 136 |
Page 137 |
Page 138 |
Page 139 |
Page 140