THE LURE OF URGENCY
Te Federal Acquisition Regulation (FAR) identifies such an urgency as “unusual and compelling urgency,” and one where the United States would be “seriously injured” unless the number of sources solicited is limited, according to FAR 6.302-2. (B-243382.3 Durodyne Inc.)
Restricting competition because an unusual and compelling urgency exists is an authorized exception to the full and open competition requirements of the Competition in Contracting Act, imple- mented at FAR 6.302-2. However, federal procurement regulations don’t define urgency as it relates to restricting compe- tition for the government’s procurement requirements. One may reason that, if one can simply explain the need to procure a particular item or service quickly, compe- tition requirements may be waived.
Te Government Accountability Office (GAO) has provided some guidance as to what circumstances may result in an unusual and compelling urgency and as we’ll see in each of the following exam- ples, unusual compelling urgency is not always defensible.
RULE NO. 1 Limiting full and open competition must not be based on a lack of advance procure- ment planning.
FAR 7.102 requires federal agencies to perform acquisition planning and conduct market research for all acquisitions. Typi- cally, acquisition planning should begin as soon as the agency need is identified, pref- erably well in advance of the fiscal year in which contract award or order placement is necessary. (FAR 7.104(a).)
Example 1. Te Navy had been working on the performance requirements for a replacement contract, issued a solicitation, realized the solicitation requirements were
74 Army AL&T Magazine Fall 2021
REMOVE BEFORE FLIGHT
The Cessna T-37 is a trainer aircraft used by the Air Force for more than 50 years, until it was retired in 2008. In 1990, the service awarded sole-source contracts to two suppliers for replacement fuel cells, but GAO determined that the contract provisions included unnecessary standards for extensive flight testing of the parts. (Photo by Harry Toneman, U.S. Air Force)
not adequately defined, and canceled the solicitation. Because these contracts would expire within a matter of weeks, perfor- mance under both contracts was extended on the basis of “urgent and compelling circumstances.”
In 1996, New Breed Leasing submitted a protest to the GAO, complaining that there was no rational basis for the sole- source extensions, and that the sole-source contract extensions resulted from a lack of planning.
In response to the protest, the Navy claimed it hadn’t realized that both solici- tations' requirements were not adequately defined until the end of July 1996. Conse- quently, because both contracts would expire Sept. 30, 1996, both required an extension for an entire year because the requirement must undergo "a thorough and comprehensive review and rewrite."
It turns out that the solicitation require- ments for the follow-on contract were identified in July 1994, the acquisition
plan was approved June 1995, proposals submitted in response to the solicitation were submitted by October 1995, and the proposal evaluation was completed by June 1996. When the contracting offi- cer sought approval from headquarters in July 1996 to proceed with negotiations, headquarters expressed its concern that the request for proposal lacked definitive task descriptions. Te Navy canceled the solici- tations on Aug. 8, 1996, and subsequently extended both contracts. In essence, the Navy realized that the solicitations were flawed more than a year after the solici- tations were issued and more than eight months after proposals were submitted.
Te protest of the Navy’s action to the GAO was sustained because the contract action resulted from a lack of advance plan- ning. (B-274201 New Breed Leasing.)
“Advance procurement planning” may appear redundant. One could reason that all planning is done in advance. But the FAR intends procurement plan- ning to be conducted well in advance;
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100 |
Page 101 |
Page 102 |
Page 103 |
Page 104 |
Page 105 |
Page 106 |
Page 107 |
Page 108 |
Page 109 |
Page 110 |
Page 111 |
Page 112 |
Page 113 |
Page 114 |
Page 115 |
Page 116 |
Page 117 |
Page 118 |
Page 119 |
Page 120 |
Page 121 |
Page 122 |
Page 123 |
Page 124 |
Page 125 |
Page 126 |
Page 127 |
Page 128 |
Page 129 |
Page 130 |
Page 131 |
Page 132 |
Page 133 |
Page 134 |
Page 135 |
Page 136 |
Page 137 |
Page 138 |
Page 139 |
Page 140 |
Page 141 |
Page 142 |
Page 143 |
Page 144 |
Page 145 |
Page 146 |
Page 147 |
Page 148 |
Page 149 |
Page 150 |
Page 151 |
Page 152 |
Page 153 |
Page 154 |
Page 155 |
Page 156 |
Page 157 |
Page 158 |
Page 159 |
Page 160 |
Page 161 |
Page 162 |
Page 163 |
Page 164 |
Page 165 |
Page 166 |
Page 167 |
Page 168 |
Page 169 |
Page 170 |
Page 171 |
Page 172 |
Page 173 |
Page 174 |
Page 175 |
Page 176