could forecast that even that much money wouldn’t be enough.
BURN RATE 101 For professional military officers, it cer- tainly isn’t easy to admit failure, or to predict that you’re going to be a failure in 18 months or less. It took us the bet- ter part of a year and about four more meetings of the non-milestone DAB to formally re-baseline the program—recal- culate and revise the costs and schedule for the remaining work—by deferring our production and recoloring the near-term money, etc. It was painful.
One of the main difficulties was not only projecting how much more money we would need to finish development, but how much more time as well. Red teams, blue teams, tiger teams—the bureaucracy assigned any number of “experts” to help us figure it all out. Te Office of Cost Assessment and Program Evaluation, back then called the Cost Analysis Improve- ment Group, was heavily involved in getting to the root causes of our troubles and identifying the resources needed to proceed. We had been spending about $10 million per month, and we were going to need about $180 million more. What no one seemed to be able to decide was how much more time should be added to the original 36-month schedule.
Tere were 40-month estimates, and 42- and 48- and finally 54-month versions of the revised EMD phase. We finally arrived at the 54-month estimate—18 additional months for the additional $180 million. How about that! We could’ve done some pretty simple math to arrive at that sched- ule figure once we got the latest revised bottom-up engineering estimate. But believe it or not, there weren’t that many people who even considered the burn rate in their estimates of the schedule needed.
Te idea of burn rate, or spending rate, was an important takeaway for me from all this. (See Figure 1.) EVM “gold cards,” provided by Defense Acquisition Univer- sity, and their published instructions tell you all about various ways to figure out a new estimate at completion (EAC). But the EVM readings and formulas available to all of us don’t adequately teach us how to estimate schedule when they take us through these concepts of planned, actual and earned value. Te squiggly lines and values typically guide us toward estima- tion of a new budget at completion or EAC, but they don’t elaborate on how much more time might be needed. And time is indeed money.
It’s possible, perhaps, to apply cost perfor- mance index and schedule performance index calculations against the original budget to project a new version of the program schedule. But current EVM instruction is really lacking when it comes to how to deal with the extra funds you receive if you’re unlucky enough to need them and lucky enough to get them.
It turns out, as I discovered during the Javelin recalculations, that once develop- ment programs get underway, their staffs of various engineers burn resources
at
a fairly consistent rate. For us, we were involved with knowledge work at that point; no missiles had yet flown. But lots of chemical, mechanical, electrical and software engineering was in flow, as well as all the work of the business types: admin, scheduling, management and indirect costs, for example.
LESSON WELL LEARNED Frequently, we work EVM problems here at the Naval Postgraduate School. I ask my students how much more money and time will be required for a program run- ning behind schedule and over budget. Unlike common stock shares’ technical
analysis charts, EVM is indeed a predic- tive tool. And as with an artillery shell just one millimeter off its deflection or azi- muth, a cost or schedule variance vectors out over distance to become quite large depending on range (or time remaining).
Most often, students come up with a nice combined index formula for a pessimistic estimate—maybe the more pessimistic, the better—but then they expect to spend many more millions of dollars in only a few months added to EMD. It just isn’t likely to happen, because practically, industry cannot simply add staff to “crash” the program and finish it rapidly. Tey’ll most likely continue at their current systemic rate of cost and schedule inef- ficiency. Hopefully, the earned value you attain during the extension will be the same or better than what it’s been so far— but we can’t expect miracles.
Tis knowledge would serve me well a few years later when I took over my own program. It was amazingly similar to the
I thought, “How could we be in so much trouble? And how could the boss know at this juncture that we were going to fail to stay within budget for the remainder of the program?”
ASC.ARMY.MIL 241
COMMENTARY
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100 |
Page 101 |
Page 102 |
Page 103 |
Page 104 |
Page 105 |
Page 106 |
Page 107 |
Page 108 |
Page 109 |
Page 110 |
Page 111 |
Page 112 |
Page 113 |
Page 114 |
Page 115 |
Page 116 |
Page 117 |
Page 118 |
Page 119 |
Page 120 |
Page 121 |
Page 122 |
Page 123 |
Page 124 |
Page 125 |
Page 126 |
Page 127 |
Page 128 |
Page 129 |
Page 130 |
Page 131 |
Page 132 |
Page 133 |
Page 134 |
Page 135 |
Page 136 |
Page 137 |
Page 138 |
Page 139 |
Page 140 |
Page 141 |
Page 142 |
Page 143 |
Page 144 |
Page 145 |
Page 146 |
Page 147 |
Page 148 |
Page 149 |
Page 150 |
Page 151 |
Page 152 |
Page 153 |
Page 154 |
Page 155 |
Page 156 |
Page 157 |
Page 158 |
Page 159 |
Page 160 |
Page 161 |
Page 162 |
Page 163 |
Page 164 |
Page 165 |
Page 166 |
Page 167 |
Page 168 |
Page 169 |
Page 170 |
Page 171 |
Page 172 |
Page 173 |
Page 174 |
Page 175 |
Page 176 |
Page 177 |
Page 178 |
Page 179 |
Page 180 |
Page 181 |
Page 182 |
Page 183 |
Page 184 |
Page 185 |
Page 186 |
Page 187 |
Page 188 |
Page 189 |
Page 190 |
Page 191 |
Page 192 |
Page 193 |
Page 194 |
Page 195 |
Page 196 |
Page 197 |
Page 198 |
Page 199 |
Page 200 |
Page 201 |
Page 202 |
Page 203 |
Page 204 |
Page 205 |
Page 206 |
Page 207 |
Page 208 |
Page 209 |
Page 210 |
Page 211 |
Page 212 |
Page 213 |
Page 214 |
Page 215 |
Page 216 |
Page 217 |
Page 218 |
Page 219 |
Page 220 |
Page 221 |
Page 222 |
Page 223 |
Page 224 |
Page 225 |
Page 226 |
Page 227 |
Page 228 |
Page 229 |
Page 230 |
Page 231 |
Page 232 |
Page 233 |
Page 234 |
Page 235 |
Page 236 |
Page 237 |
Page 238 |
Page 239 |
Page 240 |
Page 241 |
Page 242 |
Page 243 |
Page 244 |
Page 245 |
Page 246 |
Page 247 |
Page 248 |
Page 249 |
Page 250 |
Page 251 |
Page 252 |
Page 253 |
Page 254 |
Page 255 |
Page 256 |
Page 257 |
Page 258 |
Page 259 |
Page 260 |
Page 261 |
Page 262 |
Page 263 |
Page 264 |
Page 265 |
Page 266 |
Page 267 |
Page 268 |
Page 269 |
Page 270 |
Page 271 |
Page 272 |
Page 273 |
Page 274 |
Page 275 |
Page 276